Chantiers Admin EBOMAF

EBOMAF-TOGO: Installation of the Lomé-Kpalimé yard continues in serenity

EBOMAF-TOGO: Installation of the Lomé-Kpalimé yard continues in serenity

Two life bases were built in the vicinity of Lomé only for the work of the Lomé-Kpalimé road. One is located in Attiègou to Tokoin International Airport and the other in Adidogomè. EBOMAF has been deploying impressive and latest generation equipment for some time.Two large parks of materials dedicated to the construction of a modern road now stand on both sites. The company has devoted enormous resources to the acquisition of various equipment to raise this new in the construction sector in Togo.

Two more areas have been built in Bagbé since 8 June 2020. The first, which covers about two (2) hectares, will accommodate the heated power plant with an estimated production capacity of three hundred (300) tonnes per hour.

This will allow the company to have in one day a production of serious bitumen (GB) of one (1) kilometre by ten (10) metres wide or two (2) kilometres of bituminous concrete (BB). At two hundred (200) metres from the central heating plant, the second area covers eight (8) hectares. At this point, two (2) large concrete power plants and a platform for the production of cannels, edges, prefabricated dallets will be erected.

Bulldozers and other heavy equipment are already on foot on the Lomé-Kpalimé axis to ensure the installation of the site. The rumbling of these machines already gives rise to the joy of a new road infrastructure among the population.

The President and Chief Executive Officer of the EBOMAF Group, Mahamadou Bonkoungou, in person, ensures that these prerequisites for the effective start of work are not disrupted. He personally led the visit to the new crushing career in the village of Badja-Agudja thirty-five (35) kilometres northwest of the capital.

He asked the head of the town to accompany him in the extraction and processing of granite, especially since this activity is an essential part of the development of the work.

AB/JESP

Commentaires (0)

Laisser un commentaire

Vous devez être connecté pour commenter

Articles récents

A Field Mission of the Governor of the Estuary on Compensation for Affected Populations
September 26, 2025

A Field Mission of the Governor of the Estuary on Compensation for Affected Populations

Lire l'article →
Public Works test the solidity of the future bitumen on the Ntoum-Cocobeach site
July 10, 2025

Public Works test the solidity of the future bitumen on the Ntoum-Cocobeach site

Lire l'article →
... visitors online
... visitors this month