EBOMAF-BENIN: Dassa-Savalou-Djougou records exploits in its realization

EBOMAF-BENIN: Dassa-Savalou-Djougou records exploits in its realization

The works beat their full on site with the route in finished profile of 255 Km from the site Dassa-Savalou-Djougou and its three straps: Kprékété-Frontière Togo (0.8 Km), Bassila-Frontière Togo (4.7 Km), Bassila-Manigri (9.3 Km). Significant progress is being made on various fronts. Several sections are attached.



The various data on the implementation of the project are instructive. The terrace is more than 200 km away, the cement floor reaches about 160 km along the whole section. Dassa-Savalou-Kprekété axis, 131 km long is completely completed. Only remediation work remains in place. Between Kprekété and Djougou via Bassila, the technical sections are activated. The serious bitumen (GB), already done, covers 44 km and bituminous concrete (BB) about 10 km.

The application of bitumen is carried out simultaneously with the development of the site. Teams constantly take turns to maintain a constant pace of work. The construction of the straps included in this project already makes the users of the Benin-Togo line admire with regard to the bituminous concrete that is already a reality there.

WM/JE

Commentaires (0)

Laisser un commentaire

Vous devez être connecté pour commenter

Articles récents

A Field Mission of the Governor of the Estuary on Compensation for Affected Populations
September 26, 2025

A Field Mission of the Governor of the Estuary on Compensation for Affected Populations

Lire l'article →
Public Works test the solidity of the future bitumen on the Ntoum-Cocobeach site
July 10, 2025

Public Works test the solidity of the future bitumen on the Ntoum-Cocobeach site

Lire l'article →
... visitors online
... visitors this month