EBOMAF-CI: Various roads and networks (VRD) are completed in the city of Bundiali
All civil engineering activities for the development and construction of the Bundiali-Dianra road are now concentrated on this axis. In Boundiali, the capital of the Bagoué region, in the northern part of Côte d'Ivoire, various roads and networks (VRD) have just been completed. This is the first eight (8) kilometres that EBOMAF is responsible for.
The last layers of bitumen were laid on the night from Sunday, December 11 to Monday, December 12, 2022. The successful firm put double bites to achieve positive results before the end of the year.
The city now gives a proud look through its main street of twice two fully electrified tracks with a large roundabout in front of the new town hall.

From the Haidara neighbourhood to the residence of Mayor Mariatou Koné, bitumen has taken place. With this part of the project completed, the various tasks will now concern the section Bundiali - Dianra for a length of approximately eighty (84) km.
There is a real effervescence on this part of the work. The project is making significant progress. Fifty (50) works of art have already been produced and fifteen (15) works are being completed.

The marshy state of the section requires special attention. As for the actual route of the road, from Bundiali to Diana, it is almost finished. There are only a few remaining issues. The networks of the dealers, which require a displacement of the power lines or water lines, are not yet carried out.

On the Bundiali side, the cement floor began on Monday, December 19. This step precedes the application of bitumen. EBOMAF is actively involved in the timely implementation of this important project.
SS/JESP
Commentaires (0)
Laisser un commentaire
Vous devez être connecté pour commenter
Articles récents
A Field Mission of the Governor of the Estuary on Compensation for Affected Populations
Lire l'article →