The Tandjouaré-Kanté yard is experiencing a strong mobilisation of the company. Several portions of the one-hundred-and-thirty (130) kilometres are fully completed in accordance with the specifications. To date (20/05/2020), the work has recorded an overall physical progress rate of 75%. The pace of work is sustained to reach PK 130 as soon as possible.

The earthmoving and enlargement activities are already carried out over 126 km or 97%. The implementation of the Foundation is carried out on 125.425 km or 96.48%. The cement floor extends over 104.90 km or 80.69%. The Grave-Bitume (GB) reaches 93.73 km or 72.10%.

The Bituminous Concrete covered 88.90 km or 68.50%. The construction of the Peage station is estimated at 55%. Signs are expected to end the entire project.



The rehabilitation of the Tandjouaré-Kanté section is part of the dynamic of the Cinkansé-Tandjouaré section, which was led by EBOMAF. In this momentum, the Togolese corridor is in the process of turning new with a wider and more modern road. Benefiting from all the criteria for a Community way linking the port of Lomé with the country of the hinterland: Burkina Faso, Mali, Niger.

ISP

office 2013 lisans satın al

Commentaires (0)

Laisser un commentaire

Vous devez être connecté pour commenter

Articles récents

A Field Mission of the Governor of the Estuary on Compensation for Affected Populations
September 26, 2025

A Field Mission of the Governor of the Estuary on Compensation for Affected Populations

Lire l'article →
Public Works test the solidity of the future bitumen on the Ntoum-Cocobeach site
July 10, 2025

Public Works test the solidity of the future bitumen on the Ntoum-Cocobeach site

Lire l'article →
... visitors online
... visitors this month